Integrated Program Timeline & Milestones — GLPI-103

Field Value
Document ID PM-002
Version 1.0
Status Final (portfolio)
Effective Date 2026-06-29
Confidentiality Confidential — portfolio use

Change History

Version Date Author Summary
1.0 2026-06-29 Project Mgmt 초판. Phase-gate·마일스톤 일정 (illustrative)

일정은 illustrative [MOCK]. 대상자 수·비용은 REF-002 / PM-003 인용. 목표 제출 Q4 2031(CDP §9).


1. High-Level Schedule (Gantt 개요)

Year        2026  2027  2028  2029  2030  2031
Nonclinical [====]
CMC (dev)   [==========================...........]
Ph1 SAD 101    [==]
Ph1b MAD 102      [===]
   └ Gate 1/2 (PoC entry decision)  ▲
Ph2 PoC 201          [======]
   └ Gate 3 (Phase 3 invest decision)    ▲
Ph3 pivotal 301             [===========]   (52-wk treat + FU + DBL/analysis)
CSR / Module 2-5 authoring               [=====]
eCTD submission (FDA/EMA/MFDS/PMDA)             ▲ Q4 2031

2. Milestones & Phase Gates

# Milestone 시점(목표) Gate 결정 누적비용(PM-003)
M1 FIH 첫 투여 (101) 2026 H2 — —
M2 SAD 완료 (N=40) 2027 H1 Gate 1: 안전성·PK → 1b 진행 ~$3.5M
M3 MAD 완료 (N=40) 2027 H2 Gate 2: 조기효능 신호 → Ph2 진행 ~$7.5M
M4 Phase 2 PoC 완료 (N=240) 2028 H2 Gate 3: 용량–반응 → Ph3 대규모 투자 ~$23.3M
M5 Phase 3 LPLV (N=900계획/679실측) 2030 H2 — ~$91.5M
M6 Phase 3 DBL · CSR-301 2031 H1 제출 결정 —
M7 eCTD 제출 2031 Q4 — —

3. Critical Path & 비용 연계

임계경로 = Phase 2 PoC → Gate 3 → Phase 3(최장·최고비용). Gate 3 이전 단계를 작고 빠르게(REF-002 보정 N) 가져가면 임계경로 진입 전 자본 소진을 ~$13M 줄인다(PM-003 §3).

4. 연계 문서

PM-001(Charter) · PM-003(Budget) · PM-004(Risk Register) · REF-002(parameters).