Samples / GLPI-103 / program-management/PM-005_governance_and_raci.md

Governance & RACI / Phase-Gate Criteria — GLPI-103

Field Value
Document ID PM-005
Version 1.0
Confidentiality Confidential — portfolio use

Change History

Version Date Author Summary
1.0 2026-06-29 Project Management Initial governance & RACI

1. Governance Bodies

2. RACI (key deliverables)

Deliverable Clinical Biostat/DM Regulatory CMC PV PM
Protocol / SAP A/R R C I C C
CSR / TLFs A R C I C I
CDISC datasets / define I A/R C — — I
Module 2/3/5 dossier C C A/R R(M3) C C
RMP / safety C C C — A/R I
Budget / timeline / risk C C C C C A/R

(R = Responsible, A = Accountable, C = Consulted, I = Informed.)

3. Phase-Gate Decision Criteria

Gate Trigger Go criteria
Gate 1 After FIH SAD (101) Acceptable safety/PK
Gate 2 After MAD (102) Early efficacy/biomarker signal
Gate 3 After Phase 2 PoC (201) Dose–response established → commit Phase 3
Gate 4 After Phase 3 (301) Positive benefit–risk → submit

Decisions and rationale are recorded in the Decision Log (PM-DECISION). Cost context per PM-003; risks per PM-004.